S. 51st St. ARRA Project – W. Grange Ave. to
W. Loomis Rd. (STH 36)
The Village of Greendale and the City of Greenfield jointly applied for and received federal stimulus funding to assist with the reconstruction of S. 51st St. between W. Grange Ave. and W. Loomis Rd. (STH 36).
Beginning in the spring of 2010, S. 51st St. will be reconstructed with two driving lanes, bicycle accommodations, curb and gutter, drainage improvements, sidewalk improvements, enhanced signing and pavement markings. The roadway will be closed to thru traffic during construction and allow for local property access. Project work is anticipated to be completed in the fall of 2010.
W. College Ave. (CTH ZZ) ARRA Project – W. Loomis Rd (STH 36) to S. 51st St.
Milwaukee County has received federal stimulus monies for the rehabilitation of W. College Ave (CTH ZZ) from W. Loomis Rd. (STH 36) to S. 51st St.
Beginning in the spring of 2010, W. College Ave will be rehabilitated with new asphalt pavement (2 lane road), curb and gutter in some locations, storm water management ponds, drainage improvements, bicycle accommodations, school loading zone improvements, pavement markings, and signage. The roadway will be constructed in segments to allow for local traffic to access neighborhoods and the College Park elementary school property.
Residents of the "R" Section will always have access to and from their homes and emergency access to the subdivision will not be compromised. Residents of the Riverdale/Radburn area will need to use the Loomis Rd. intersection during the western phase of the project. Residents of the "R' section streets that intersect Root River Dr. will always have the option of using the Russell Dr. exit to S. 51st. St. and at least one of the Root River Dr. exits onto W. College Ave. Residents who live in the lower "O" Section will need to use W. Ramsey Ave. to leave the subdivision during the western phase of the project.Village staff will work closely with Milwaukee County (the owner of W. College Ave.) and all contractors to minimize any inconvenience to the public.
W. Loomis Rd. (STH 36) Rehabilitation Project – South Village Limits to North Village Limits
The Wisconsin Department of Transportation will be rehabilitating the asphalt pavement on STH 36 through the Village of Greendale in the 2010 construction season. Improvements include base repairs, new asphalt pavement, signal and geometric improvements at intersections, signing and pavement markings.
Root River Parkway Bridge Replacement ARRA Project ¼ Mile West of STH 36
Milwaukee County has received federal stimulus monies to replace the bridge over the Root River on the Root River Parkway during the summer of 2010. It is anticipated that the bridge work will necessitate the closure of the Root River Parkway road between STH 36 and S. 76th St. (CTH U) while the work is being done.
The Village of Greendale and the City of Greenfield jointly applied for and received federal stimulus funding to assist with the reconstruction of S. 51st St. between W. Grange Ave. and W. Loomis Rd. (STH 36).
Beginning in the spring of 2010, S. 51st St. will be reconstructed with two driving lanes, bicycle accommodations, curb and gutter, drainage improvements, sidewalk improvements, enhanced signing and pavement markings. The roadway will be closed to thru traffic during construction and allow for local property access. Project work is anticipated to be completed in the fall of 2010.
W. College Ave. (CTH ZZ) ARRA Project – W. Loomis Rd (STH 36) to S. 51st St.
Milwaukee County has received federal stimulus monies for the rehabilitation of W. College Ave (CTH ZZ) from W. Loomis Rd. (STH 36) to S. 51st St.
Beginning in the spring of 2010, W. College Ave will be rehabilitated with new asphalt pavement (2 lane road), curb and gutter in some locations, storm water management ponds, drainage improvements, bicycle accommodations, school loading zone improvements, pavement markings, and signage. The roadway will be constructed in segments to allow for local traffic to access neighborhoods and the College Park elementary school property.
Residents of the "R" Section will always have access to and from their homes and emergency access to the subdivision will not be compromised. Residents of the Riverdale/Radburn area will need to use the Loomis Rd. intersection during the western phase of the project. Residents of the "R' section streets that intersect Root River Dr. will always have the option of using the Russell Dr. exit to S. 51st. St. and at least one of the Root River Dr. exits onto W. College Ave. Residents who live in the lower "O" Section will need to use W. Ramsey Ave. to leave the subdivision during the western phase of the project.Village staff will work closely with Milwaukee County (the owner of W. College Ave.) and all contractors to minimize any inconvenience to the public.
W. Loomis Rd. (STH 36) Rehabilitation Project – South Village Limits to North Village Limits
The Wisconsin Department of Transportation will be rehabilitating the asphalt pavement on STH 36 through the Village of Greendale in the 2010 construction season. Improvements include base repairs, new asphalt pavement, signal and geometric improvements at intersections, signing and pavement markings.
Root River Parkway Bridge Replacement ARRA Project ¼ Mile West of STH 36
Milwaukee County has received federal stimulus monies to replace the bridge over the Root River on the Root River Parkway during the summer of 2010. It is anticipated that the bridge work will necessitate the closure of the Root River Parkway road between STH 36 and S. 76th St. (CTH U) while the work is being done.