Construction Update for November 3
November 03, 2010
Loomis Road: The Wisconsin Department
of Transportation Loomis Rd. Project is nearing
completion at least for this seaon. Contractors are
working overtime and on Saturdays in an attempt to
complete as much work as possible before the winter
weather sets in. There are several days worth of
concrete curb, sidewalk and median work to be completed
before the final asphalt overlay and pavement marking
work can be done. The traffic signals and intersection
lighting work can be accomplished in any kind of
weather so the main focus will be on opening all lanes
to traffic. It is quite likely that much of the
landscaping work will need to be held off until the
spring of 2011. Driving conditions should improve
greatly over the next two weeks as November 15th is the
target date for completion. Please continue to be extra
cautious and patient in work zones.
All other road construction projects in the Village are now complete.
All other road construction projects in the Village are now complete.
Construction Update for September 23
September 23, 2010
College Avenue: The final layer of
asphalt is now in place and the intersection of College
Ave and S, 51st St. has been milled, reshaped and new
aspalt has been placed. The remaining pavement marking,
signage and landscaping will be completed within the
next week.
S.51st Street: Approaches and sidewalks are now completed. Landscaping, signage and the first layer of asphalt is scheduled to be completed before Oct. 4th. Of course thats weather permitting.
Loomis Road: Most work has transitioned to the outer lanes. Long delays will continue at the local road intersections near Grange Ave for several weeks as lane widening work continues. Please remember to avoid that area if possible and expect delays. The Village is working with the project owner, the State of Wisconsin to minimize traffic problems during this massive construction project.
S.51st Street: Approaches and sidewalks are now completed. Landscaping, signage and the first layer of asphalt is scheduled to be completed before Oct. 4th. Of course thats weather permitting.
Loomis Road: Most work has transitioned to the outer lanes. Long delays will continue at the local road intersections near Grange Ave for several weeks as lane widening work continues. Please remember to avoid that area if possible and expect delays. The Village is working with the project owner, the State of Wisconsin to minimize traffic problems during this massive construction project.
Construction Update for September 13
September 13, 2010
College Avenue: The first layer of
asphalt is now in place on the east phase of the
project. Look for finish landscaping, fence
installation and the top layer of asphalt to be
completed over the next two weeks.
S.51st Street: The curb is now in place and the week of Sept. 13 will see the approaches to driveways constructed along with utility adjustments. Asphalt will follow soon after.
Loomis Road: The enormity of the project may make it seem like it will never get done. However, there has been steady progress and the project is on track for a mid-late fall completion. Please use alternate routes when possible.
S.51st Street: The curb is now in place and the week of Sept. 13 will see the approaches to driveways constructed along with utility adjustments. Asphalt will follow soon after.
Loomis Road: The enormity of the project may make it seem like it will never get done. However, there has been steady progress and the project is on track for a mid-late fall completion. Please use alternate routes when possible.
Construction Update for August 24
August 24, 2010
Here is the latest update for all of the 2010 Paving
Projects within the Village.
College Avenue: Landscaping and grass seeding has been completed around the stormwater retention ponds and curb will be installed this week on the east portion of the project. Finish grading on the east phase roadbed is complete.
S.51st Street: The grading of the roadbed is complete and curb installation is scheduled for the week of Sept. 6. The base course of asphalt will follow shortly after.
Loomis Road: This project is slowly being completed from the nort to the south but much work remains. Work will transition to the outer lanes within several weeks. Please remain alert when driving in any construction zone!.
College Avenue: Landscaping and grass seeding has been completed around the stormwater retention ponds and curb will be installed this week on the east portion of the project. Finish grading on the east phase roadbed is complete.
S.51st Street: The grading of the roadbed is complete and curb installation is scheduled for the week of Sept. 6. The base course of asphalt will follow shortly after.
Loomis Road: This project is slowly being completed from the nort to the south but much work remains. Work will transition to the outer lanes within several weeks. Please remain alert when driving in any construction zone!.
Construction Update for August 11
August 11, 2010
Here is the latest update for all of the 2010 Paving
Projects within the Village.
College Avenue: The stormwater retention ponds are complete with topsoil and grass seed now being installed around the perimeter. Sod work is complete on the west portion with road base work continuing on the east portion. Look for the west phase curb to be installed very soon with a base course of asphalt to follow directly after.
S.51st Street: The road elevation and base work is nearly complete with just a short stretch needing to be finished near Loomis Rd. Additional road bed material will be installed soon with curb to follow.
Loomis Road: Work continues in the inner lanes. Several areas are now receiving a base layer of asphalt. Reshaping of the intersection at College Ave. is nearing completion and the crews will be moving to the intersection of Ramsey Ave. and then Grange Ave. Traffic restrictions are numerous and delays are to be expected especially when work is being done in intersections. The State of Wisconsin DOT urges motorists to be very cautious in work zones and use alternate routes when possible.
2010 Greendale Paving Projects: All portions of the 2010 Project are now complete.
College Avenue: The stormwater retention ponds are complete with topsoil and grass seed now being installed around the perimeter. Sod work is complete on the west portion with road base work continuing on the east portion. Look for the west phase curb to be installed very soon with a base course of asphalt to follow directly after.
S.51st Street: The road elevation and base work is nearly complete with just a short stretch needing to be finished near Loomis Rd. Additional road bed material will be installed soon with curb to follow.
Loomis Road: Work continues in the inner lanes. Several areas are now receiving a base layer of asphalt. Reshaping of the intersection at College Ave. is nearing completion and the crews will be moving to the intersection of Ramsey Ave. and then Grange Ave. Traffic restrictions are numerous and delays are to be expected especially when work is being done in intersections. The State of Wisconsin DOT urges motorists to be very cautious in work zones and use alternate routes when possible.
2010 Greendale Paving Projects: All portions of the 2010 Project are now complete.
Construction Update for August 3
August 03, 2010
Here is the latest update for all of the 2010 Paving
Projects within the
Village.
College Avenue: The west detention pond is excavated and will recieve a clay liner soon. Pulverizing of the old pavement and grubbing work is completed on the east portion. Look for the east detention pond excavation work and curb installation to begin soon. Sod restoration is well underway east of 60th St.
S.51st Street: Road bed stabilization continues in several areas as well as drainage improvement excavation. Please remember that the road is only open to local traffic.
Loomis Rd.... Work on the inner lanes, turn lanes and storm sewers continues for a few more weeks before work switches to the outer lanes. Please use caution in all work zones and use alternate routes when possible.
2010 Greendale Paving Projects: The 2010 Greendale Paving Program is now complete. Cotractors may still be seen watering/replacing sod in a few spots. Thanks to all residents for their cooperation and patience during construction.
College Avenue: The west detention pond is excavated and will recieve a clay liner soon. Pulverizing of the old pavement and grubbing work is completed on the east portion. Look for the east detention pond excavation work and curb installation to begin soon. Sod restoration is well underway east of 60th St.
S.51st Street: Road bed stabilization continues in several areas as well as drainage improvement excavation. Please remember that the road is only open to local traffic.
Loomis Rd.... Work on the inner lanes, turn lanes and storm sewers continues for a few more weeks before work switches to the outer lanes. Please use caution in all work zones and use alternate routes when possible.
2010 Greendale Paving Projects: The 2010 Greendale Paving Program is now complete. Cotractors may still be seen watering/replacing sod in a few spots. Thanks to all residents for their cooperation and patience during construction.
Construction Update for July 21
July 21, 2010
Here is the latest update for all of the 2010 Paving
Projects within the Village.
College Avenue: Landscaping work is underway on the west portion of the project. The east phase grubbing and pavement removal will begin during the week of July 26. The road will remain closed to all but local traffic for the duration of the project to ensure the safest possible work zone.
S.51st Street: The pavement has now been removed and stormwater, sanitary sewer and water main adjustments are underway. Road bed and curb installation will begin soon. The road is closed to all but local traffic.
Loomis Road: Work continues on the inside lanes on the entire 8 mile project. Traffic is slow and delays are frequent. Please excersize caution when traveling in construction zones. As soon as paving is completed on the iside lane the work will move to the outer lanes.
2010 Greendale Paving Projects: The 2010 Paving Program is essentially complete. All project streets are now paved with only some sod work to be completed on Moorehead Ln. A contractor will pave the asphalt paths in the area of the Middle School within a few days and a small amout of cracksealing on select streets is scheduled to be done by the end of the month.
College Avenue: Landscaping work is underway on the west portion of the project. The east phase grubbing and pavement removal will begin during the week of July 26. The road will remain closed to all but local traffic for the duration of the project to ensure the safest possible work zone.
S.51st Street: The pavement has now been removed and stormwater, sanitary sewer and water main adjustments are underway. Road bed and curb installation will begin soon. The road is closed to all but local traffic.
Loomis Road: Work continues on the inside lanes on the entire 8 mile project. Traffic is slow and delays are frequent. Please excersize caution when traveling in construction zones. As soon as paving is completed on the iside lane the work will move to the outer lanes.
2010 Greendale Paving Projects: The 2010 Paving Program is essentially complete. All project streets are now paved with only some sod work to be completed on Moorehead Ln. A contractor will pave the asphalt paths in the area of the Middle School within a few days and a small amout of cracksealing on select streets is scheduled to be done by the end of the month.
Construction Update for July 8
July 08, 2010
Here is the latest update for all of the 2010 Paving
Projects within the Village.
College Avenue: The curb and stormwater work for Phase 1 is complete and the first layer of asphalt will be installed during the week of July 12. Asphalt will be placed from Loomis Rd. to the limits of Phase 1, the east driveway at College Park School. Phase 2 from College Park School to S.51st St. will begin within a few weeks.
S.51st Street: The road remains closed to all but local traffic. Pavement removal has begun and the re-shaping of the Loomis Rd. Intersection is underway.
Loomis Road: Work continues on the inner lanes from Hwy 100 to S. 27th St.. The amount of construction activity coupled with slow moving traffic and long waits at traffic signals have created delays for motorists. The Wisconsin DOT urges motorists to be aware of changing traffic conditions and people in the work zones. Using alternate routes is recommended.
2010 Greendale Paving Project: Paving is complete on Broad St. and Edgehill Rd. The work on Moorehead Ln. is progressing well with the curb/approach/sidewalk replacements due to be completed during the week of July 12. Residents are reminded that the concrete must cure for 1 week before vehicles may drive over it. Once the forms are removed residents may begin parking on street again but not on new concrete. Milling of the old pavement and placing new aspalt will happen in a few weeks and the whole paving process takes just a few days. This is a complex project and the Village is working with the contractor to minimize inconvenience to residents on the street. Thanks for your patience!
College Avenue: The curb and stormwater work for Phase 1 is complete and the first layer of asphalt will be installed during the week of July 12. Asphalt will be placed from Loomis Rd. to the limits of Phase 1, the east driveway at College Park School. Phase 2 from College Park School to S.51st St. will begin within a few weeks.
S.51st Street: The road remains closed to all but local traffic. Pavement removal has begun and the re-shaping of the Loomis Rd. Intersection is underway.
Loomis Road: Work continues on the inner lanes from Hwy 100 to S. 27th St.. The amount of construction activity coupled with slow moving traffic and long waits at traffic signals have created delays for motorists. The Wisconsin DOT urges motorists to be aware of changing traffic conditions and people in the work zones. Using alternate routes is recommended.
2010 Greendale Paving Project: Paving is complete on Broad St. and Edgehill Rd. The work on Moorehead Ln. is progressing well with the curb/approach/sidewalk replacements due to be completed during the week of July 12. Residents are reminded that the concrete must cure for 1 week before vehicles may drive over it. Once the forms are removed residents may begin parking on street again but not on new concrete. Milling of the old pavement and placing new aspalt will happen in a few weeks and the whole paving process takes just a few days. This is a complex project and the Village is working with the contractor to minimize inconvenience to residents on the street. Thanks for your patience!
Construction Update for June 20
June 20, 2010
College Avenue: The work on the west
portion of this two-part project is proceeding as
planned. The road is shaped and nearly ready for curb
installation. The excavation of the
west stormwater retention pond has begun.
The road is open to local traffic
only.
S.51st Street: Construction begins on June 21. The road will only be open to local traffic.
Loomis Road: This Wisconsin DOT project is well underway and lane restrictions are numerous. Stormwater improvements, pavement milling and lots of orange barrels make for a busy work zone. Please use caution when traveling in work zones and obey the reduced speed limits.
2010 Greendale Paving Project: The curb, sidewalk, approach and underground work on the local streets is nearly complete. Expect milling and paving to begin within the next two weeks. Remember...If you cannot use your driveway due to construction you may call the Greendale Police Department at 423-2121 for permission to park on the street for free.
S.51st Street: Construction begins on June 21. The road will only be open to local traffic.
Loomis Road: This Wisconsin DOT project is well underway and lane restrictions are numerous. Stormwater improvements, pavement milling and lots of orange barrels make for a busy work zone. Please use caution when traveling in work zones and obey the reduced speed limits.
2010 Greendale Paving Project: The curb, sidewalk, approach and underground work on the local streets is nearly complete. Expect milling and paving to begin within the next two weeks. Remember...If you cannot use your driveway due to construction you may call the Greendale Police Department at 423-2121 for permission to park on the street for free.
Construction Update for June 9
June 09, 2010
College Ave.: As of June 9 the
grubbing and drainage work has begun. The stormwater
retention pond at the southeast corner of College ave.
and Loomis Rd. will be excavated soon. Please remember
that College Ave is only open to local traffic.
S. 51st St.: Work is set to begin the week of June 14. Storm sewer reconstruction is up first followed by curb work and pavement removal. S. 51st St. will only be open to local traffic and motorists are urged to find alternate routes for the duration of the project.
Loomis Rd.: Work has begun on the Loomis rd project and expect thingds to ramp up quickly over the next few weeks. Expect delays, lane closures and reduced speed limits during this huge State of Wisconsin DOT project.
2010 Greendale Paving Projects: Preliminary storm and sanitary sewer work is underway. Sidewalk removal and replacement will begin the week of June 14. Please watch out for construction workers and traffic.
S. 51st St.: Work is set to begin the week of June 14. Storm sewer reconstruction is up first followed by curb work and pavement removal. S. 51st St. will only be open to local traffic and motorists are urged to find alternate routes for the duration of the project.
Loomis Rd.: Work has begun on the Loomis rd project and expect thingds to ramp up quickly over the next few weeks. Expect delays, lane closures and reduced speed limits during this huge State of Wisconsin DOT project.
2010 Greendale Paving Projects: Preliminary storm and sanitary sewer work is underway. Sidewalk removal and replacement will begin the week of June 14. Please watch out for construction workers and traffic.
Construction Update for May 28
May 28, 2010
The county has planned improvements to College Avenue
to begin shortly. The plan is for the construction to
begin on Tuesday, June 1st. Signs will be posted next
week closing College Avenue from Loomis Road to the
school. Local access will be allowed but it is
recommended that you plan ahead and use alternate
routes, click here for a detour map.
Construction Update: May 20, 2010
May 20, 2010
Root River Parkway Bridge Replacement
Construction began on May 18, 2010 and Root River Parkway between Loomis Rd. and S. 76th St. is now closed for the summer and into the fall.
W Loomis Rd. Project
The Loomis Rd. project has begun as of May 18, 2010. Even though the project will be constructed under traffic motorists are urged to find alternate routes if possible. Times of traffic stoppage and delay's are inévitable during a project of this size. Please remember that this work is a State of Wisconsin ARRA Project and that the Village of Greendale has no control over the methods of construction used or the timetable set by the contractor. As always please be patient and alert in work zones.
Construction began on May 18, 2010 and Root River Parkway between Loomis Rd. and S. 76th St. is now closed for the summer and into the fall.
W Loomis Rd. Project
The Loomis Rd. project has begun as of May 18, 2010. Even though the project will be constructed under traffic motorists are urged to find alternate routes if possible. Times of traffic stoppage and delay's are inévitable during a project of this size. Please remember that this work is a State of Wisconsin ARRA Project and that the Village of Greendale has no control over the methods of construction used or the timetable set by the contractor. As always please be patient and alert in work zones.
